Castings arrived late, at the old price, and one batch without a certificate
DocReveal reads the invoice next to the framework contract, the amendment from an e-mail, the purchase order and the delivery note. It finds the old price, works out the contractual late-delivery penalty and holds back payment for the batch without a certificate.
fictional example€4,440on one invoice+ €16,320 withheld until the certificate arrives
Manufacturing & purchasing
Invoice FV-26-0877 – don’t pay it as invoiced
Ferrostella Metal a.s. · €43,200 excl. VAT fictional example
DocReveal reads the invoice next to the framework contract, the amendment from an e-mail, the purchase order and the delivery note. It finds the old price, works out the contractual late-delivery penalty and holds back payment for the batch without a certificate.
-
Old price – amendment No. 2 applies−€2,400
The invoice charges €54.00 a piece; €51.00 has applied since 1 July.
€3.00 × 800 pcs = €2,400
-
Penalty for 10 days – Art. 5.4−€2,040
Confirmed on 1 Sep, due within 15 working days (22 Sep), delivered on 2 Oct.
10 days × 0.5% = 5% × €40,800 = €2,040
-
Batch 2 without a certificate – Art. 5.6withhold €16,320
Don’t accept it, keep it out of production and don’t pay yet. The delay keeps running.
320 pcs × €51.00 = €16,320
To pay now€22,440
Claim to the supplier – draft · block batch 2 in the warehouse · approve the payment